Process in progress
We continue to manage every detail to ensure solid and sustainable development. Our team works in the various phases of the project with a clear vision of quality and commitment.
Progress in construction work
At The Reef, we continue to progress steadily in the construction of this exclusive development in Playa Bonita, Las Terrenas. Below, we share the most recent work carried out on the site:
Earth Movement
of Lands
Cleaning and clearing completed in the areas of buildings CN, D, E, and F.
The formation of the platform of Building D was successfully completed on January 13, 2025.
A total of 1,500 m² of work platform has been prepared for soil improvement.
Improvement
of Soils
Completed the geotechnical survey campaign of Stage 1.
Design and installation in progress of gravel columns for the buildings CN, D, E, and F.
Since January 31, 300 linear meters of gravel columns have been executed, reaching 94% of the total planned.
Supplementary Works
Access from Av. Los Nómadas has been improved, facilitating transportation of materials and reducing the impact on the community.
Surveying work has begun for the planning of new accesses and future stages of the project.
We continue to make progress in each phase with a focus on quality, sustainability, and efficiency. We will soon share more updates on the progress of the work.
Next Steps
Every advance in The Reef brings us closer to the realization of an exclusive and sustainable development in Playa Bonita, Las Terrenas. We will continue to share detailed information about the next phases of the project, ensuring that our investors and clients are aware of the progress at each stage.